Reading 132/33kv Supply Upgrade

This project involved installation of dual circuit 132 kv from Reading Town to Reading Main sub stations, to upgrade the supply. This project was executed by 20 of our team members for our client, SSE.

Since 2012

MBS Construction was responsible for the installation of a dual circuit 132kv plus coms and various circuits of 33kv along the route from Reading Town to Reading Main. The project involved working through 70% carriageway lane closures and two/multi way lights 30% grass in park land 4km running from Reading main sub to Reading town sub.

Project foreman Gus Sunderland project managed five excavation gangs, two tarmac gangs, three grabs, two runners and two-yard men.

Project Details

  • Client: SSE
  • Project Manager: Laurence Sunderland
  • Site Supervisor: Gus Sunderland
  • Team Size: 20 people
  • Start Date: February 2019
  • Completion Date: TBC
View All Projects